Late-autumn light on a cedar-shingle home's covered brick entry, limestone steps and curved front walk beside a copper-leaved maple.

Downtown Downers Grove's New Shade Corners Were Built for the Long Haul, and They Debut in Winter

October 29, 2026

"We're hoping that these shade structures and flexible amenity areas live on for a long time," Commissioner Leslie Sadowski-Fugitt said before the Village Council voted in April, as My Suburban Life reported. "So there is a high likelihood that they'll live beyond potentially some of the businesses we have today as things evolve."

That quote explains the fenced-off corners on Main Street this fall better than any rendering does. The Village is spending $3,608,881.40 to turn five pieces of downtown pavement into permanent outdoor rooms with seat walls, planters, trees and lighted shade structures. Village staff told the council they expected no change in food and beverage tax revenue from them. The council approved the money anyway, on the view that the corners would stay useful through decades of downtown turnover. The Village's schedule has them finishing in November, which means their first season comes with Santa visits and wagonette rides instead of patio weather.

Where the Five Corners Are, and How Far Along Each One Is

The 2025 Guiding DG Streetscapes Plan picked five downtown spots as Flexible Amenity Areas. Its stated uses are outdoor dining, casual seating, community gatherings and public art. Crews started on the east side of Main Street in July and moved to the west side in late September.

Corner Next door, per the Village's contract memo Status in the Village's October 23 update
Northeast corner of Maple and Main Foxtail East side masonry done; planter beds getting black dirt
Northeast corner of Curtiss and Main Pierce Tavern East side masonry done; planter beds getting black dirt
Southeast corner of Burlington and Main Not named East side masonry done; planter beds getting black dirt
West side of Main, north of Curtiss Wasabi Last footings being poured; knee wall foundations and concrete underway
Burlington, west of Main, by the library entrance Not named Knee wall and curb done; sidewalk and masonry continuing

The east side corners are close to done and waiting on landscaping. The two west side sites started later. Sawcutting began the week of September 25, removals followed the week of October 2, and the Village's October 9 update reported the underground storm and water work finished. These are the two sites that will decide whether the project finishes on time. The Village's project page says all work depends on weather and that schedules can change. So the November finish date is a target.

What $3.6 Million Buys at Each Corner

All five sites get a shade structure. The contract also covers a shared list of improvements at each one:

  1. Masonry seat walls and new sidewalk
  2. Trees, landscaping, planters and underground irrigation
  3. Benches and trash and recycling receptacles
  4. Bollards and gateway signs
  5. Bases for sculpture
  6. Utility and electrical work, including lights and solar panels built into the shade structures

The sculpture bases are in the contract, but the sculptures are not. The renderings show art on the corners, and the contract drawings leave the artwork out. When the fencing comes down, you may see empty pedestals waiting for art.

Some of the old streetscape is going away to make room. The memo lists four streetlights coming out: one at the Wasabi site, one at the Pierce Tavern corner and two at the Foxtail corner. The Village's overview of the Streetscapes Plan says some on-street parking spaces may be removed permanently as downtown adds outdoor cafe space. No figure has been published for how many spaces these five corners take.

The Shade Structures Doubled the Price

The council set aside $1,800,000 in the fiscal year 2026 Capital Fund for this project. The winning bid from Landmark Contractors, Inc. of Huntley came in at about twice that, and staff said the rest could come from the same Capital Fund. The vote was 5–2.

Most of the debate was about the shade structures. Commissioner Martin Tully supported the concept and building all five corners at once, but not the cost. "We originally contemplated this being about $1.8 million in terms of what was in our budget. What's now on the table is double that," he said, according to My Suburban Life. Commissioner Tammy Sarver had said at the previous week's meeting that outdoor umbrellas could do the same job, the outlet reported.

Commissioner Chris Gilmartin called the shade structures a "core design element." In the same My Suburban Life story, he described the areas as "investments in the economic engine for downtown" that "generate sales tax, food and beverage, property tax revenue."

Staff's own numbers took a narrower view of revenue. When the council asked for the projected increase in food and beverage tax, the memo answered that staff was "not projecting any change." So the case for the extra $1.8 million rests on the argument Sadowski-Fugitt made. Umbrellas go back into storage, and a patio can close when its restaurant does. A brick seat wall under a lighted, solar-equipped canopy at Curtiss and Main stays part of the street no matter which business is next door. The council chose that kind of permanence at Maple, Curtiss and Burlington, and on the west side of Main.

Their First Season Is the Holidays

A project scheduled to end in November means none of these corners will see the summer outdoor dining season they were designed for until 2027. The first stretch of downtown activity around them will be the Downtown Downers Grove Management Corp. holiday calendar, which puts Main Street foot traffic on the same blocks:

  • Friday, November 27, 4:30 p.m.: the Village Tree Lighting Ceremony at the Main Street Train Station
  • November 27 to December 13: the Holiday Window Contest, open Fridays through Sundays
  • November 27 to December 31: Candy Cane Cash
  • Saturday, November 28, 10 a.m. to 9 p.m.: Small Business Saturday
  • Weekends from November 28 to December 20, 1 to 4 p.m.: free visits with Santa
  • Sunday, November 29, 1 to 4 p.m.: free wagonette rides, boarding at 1028 Curtiss Street
  • Thursday, December 10, 5 to 8 p.m.: Merry Madness

Downtown Downers Grove Management Corp. says all events are subject to change, and some listings still say details are coming. The tree lighting takes place at the Main Street Train Station, and three of the five new corners sit along Main at Burlington, Curtiss and Maple, a short walk from the station.

The same group's 2027 list starts with Ice Fest, followed by the Spring Scavenger Hunt, FoundersFest and the Wine Walk. That puts a winter event on the calendar for the corners months before their first full outdoor dining season.

If you live near Curtiss and Main and want to know how this kind of downtown investment shows up in your home's value, Jeff / Amjad Salhani & Associates knows these blocks well. Let's connect: get your free home valuation.